Preston's Mohegan Riverwalk Deal Still Hasn't Closed. Here's What That Means for Your Tax Bill.

At Preston's Board of Finance public hearing on April 23, 2026, resident Stephen Ballirano asked two questions. How likely was the Riverwalk land transfer to go through, and how soon would its tax revenue show up once the property reached the grand list? Selectwoman Sandra Allyn-Gauthier gave him the town's numbers. Six of the seven parcels had been cleared by DEEP. The property's estimated appraised value was $14 million, and first-year taxes would come to about $80,000.

That figure matters more than any rendering of a hotel or marina. For years the Mohegan Tribe's planned development on the former Norwich State Hospital grounds has been described as the project that would reshape Preston's tax base. The town's own near-term estimate is far smaller. As of the end of September 2026, the land hasn't changed hands. If you're comparing Preston with neighboring towns, budget for the tax bill Preston has now. The one Riverwalk might eventually support is still years off.

The Deal Was Priced for a Closing in 2018

When Preston and the Mohegan Tribe formalized the agreement in April 2017, the Norwich Bulletin reported that a maximum $600 million buildout could bring the town $43 million in taxes over 10 years. That projection assumed a 23-mill tax rate and conveyance of the land in 2018. Construction was estimated at $200 million to $600 million, with 200 to 700 full-time jobs.

Here is how those assumptions compare with the record in 2026.

2017 projection 2026 record
Conveyance year 2018, assumed Not closed as of late September 2026
Tax rate used 23 mills 25.52 mills adopted for FY2026–27
Tax revenue $43 million over 10 years at maximum buildout About $80,000 in year one, on a $14 million estimated appraisal
Construction Start within 3 years of closing Three-year clock not yet running because closing hasn't happened

The two revenue figures measure different things. The $43 million assumed a finished project at full scale. The $80,000 estimate covers land that hasn't been built on. The distance between them is mostly time, and none of that time can begin until the deed transfers.

Why the Closing Keeps Moving

The cleanup itself is done. Preston spent more than 15 years cleaning up its 398-acre share of the hospital property. The work used more than $30 million in state and federal grants plus $2.5 million in town money and was finished in October 2025, according to The Day. The town is keeping 5 acres and conveying 393 to the Tribe.

What's left is closing paperwork, and Preston Redevelopment Agency minutes show the dates sliding:

  • July 8, 2026: The agency hoped for conveyance around August 15, after a Notice of Sale and the mandatory 30-day wait. It also began planning a site event with the Tribe that would include federal, state and local officials.
  • July 31, 2026: The Notice of Sale went to the Tribe, with closing set for Thursday, September 3 at Shipman & Goodwin's Hartford office.
  • August 12, 2026: All environmental tasks were reported complete. Three easements still had to be agreed and approved before closing: one for stormwater management access, one for access to the sewer pump station, and one for access to landlocked parcels inside Parcel Two.
  • August 26, 2026: The Tribe asked for a meeting about issues that had come up in negotiations.
  • September 23, 2026: The closing checklist still included renewing a stormwater permit and reseeding slopes. The agency met in executive session on the Property Disposition and Development Agreement and took no action.
  • September 30, 2026: A special-meeting agenda again listed Riverwalk negotiations for executive session.

The stormwater permit shows how a small site issue can hold up a large deal. According to Preston Redevelopment Agency minutes, the town's permit has to be closed before conveyance and can't be transferred to the Tribe. Closing it requires 70% green coverage across the whole site and repairs to washed-out areas. After one storm, a road on the property washed out for roughly 200 to 350 feet. Crews regraded it in late August. Grass has to grow back before the permit can close.

The Development Clock Hasn't Started

Under the 2017 agreement, construction starts within three years of closing and finishes within six years of closing. Every deadline is counted from the closing date, and that date hasn't been set.

The Tribe's project page describes Preston Riverwalk as a planned non-gaming destination with indoor and outdoor attractions, a hotel, retail, restaurants, housing, a marina and an RV park. The page is undated, describes planned components, and gives no tenants, contractor or opening date.

Work on the town's side is also still on paper. In December 2025 the State Bond Commission approved $400,000 for the town-owned pump station on the hospital site. The Day reported in April 2025 that Riverwalk is expected to substantially increase demand at that station, which today handles only a small flow under an agreement with the Southeastern Connecticut Regional Resource Recovery Authority. As of July 2026, the paperwork for that grant and for a Community Investment Fund grant of about $1.6 million was still being finalized. Across the town line, Norwich and the Norwich Community Development Corp. hired IMEG Consultants Corp. in August. IMEG will study 49.65 acres of the old hospital property on Route 12 and look for uses that complement Riverwalk. The study is funded by a $250,000 state grant and is expected to take eight to nine months.

What Protects the Town in the Meantime

The town still has protection if the project stalls. Under the 2017 terms, the Tribe pays a nominal $1, backed by an $11 million letter of credit. If the Tribe builds nothing, Preston collects that $11 million and still collects property taxes on the land. The 2016 memorandum of understanding split the security into $2 million for a state loan and $9 million to cover construction. It also kept the project subject to Preston property taxes at the regular assessed value and mill rate.

The 2026 figures differ slightly. At the April 23 hearing, Board of Finance Chairman Sawyer said the numbers "are not exact yet" and that the town expects "$12 million in Escrow." Until the final agreement is public, treat both the $11 million and the $12 million as reported figures, not settled ones.

What Your Preston Tax Bill Looks Like in 2026

The Riverwalk delay affects buyers through the budget. Preston's Board of Finance set the FY2026–27 mill rate at 25.52 on July 9, 2026, after voters approved the school budget 312 to 223. The FY2025–26 rate was 25.11. The first proposal this spring was 26.78 mills. It came down to 25.71 after the board put $700,000 in supplemental state aid toward tax relief, and then to 25.52 after the referendum process. On June 3 the original school budget failed by six votes. The board then cut $118,100, bringing it to $15,422,645.

No revaluation caused this year's increase. According to the Town of Preston's revaluation RFP, Preston last revalued on October 1, 2022, and its next revaluation takes effect October 1, 2027. The rate rose against assessments that haven't changed, which means the higher rate reflects higher spending, not a reset in values. In a hypothetical example, a home assessed at $250,000 would pay about $102 more at 25.52 mills than at 25.11.

Now compare that with Riverwalk's first year. The proposed FY2026–27 budget planned to raise about $17.05 million from property taxes before later revisions. An $80,000 first-year contribution is less than half of one percent of that amount. Even after the land transfers, its early tax bill won't noticeably change the rate a homeowner pays.

The town's own budget treats Riverwalk as a future project. The FY2026–27 budget cut Riverwalk cleanup and legal costs by $136,000 as that work wrapped up. The budget presented at the May 26 annual town meeting proposed $77,819 for possible Riverwalk-related labor and $114,000 toward the 2027 revaluation.

For a buyer, that means two things to watch:

  1. The closing date. Once the deed transfers, the three-year construction deadline starts. Until then, Riverwalk generates no tax revenue.
  2. The October 1, 2027 revaluation. Assessments will reset. Whatever you pay in 2026, budget for a different tax bill when the new values take effect.

Quick Answers

Has the Mohegan Tribe taken ownership of the Riverwalk land? Not as of the most recent public record. The Redevelopment Agency was still negotiating in executive session on September 23 and had another session scheduled for September 30, 2026.

Will Riverwalk lower Preston's mill rate? Not in the near term. The town estimates about $80,000 in first-year taxes on the undeveloped land. Larger revenue depends on construction, and construction can't start until closing.

Is the land taxable? Under the agreement terms reported since 2016 and 2017, yes. The project is subject to Preston property taxes at the regular assessed value and mill rate.

What happens if the Tribe never builds? The town would draw on the letter of credit, reported at $11 million in 2017 and described as $12 million in escrow at an April 2026 hearing. It would also continue collecting property taxes on the land.

If you're thinking about buying in Preston, or selling a home there, Riverwalk will likely come up in the conversation. I'll help you sort out which numbers are confirmed and which are still projections, and what the 2027 revaluation could mean for your budget. Let's Connect with Skyla Gagnon before you make an offer.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.